Violation Detail
Standard Cited: 19100179 J03 Overhead and gantry cranes.
Inspection Nr: 922655.015
Citation: 02004
Citation Type: Other
Abatement Status: Abatement Completed
Initial Penalty: $0.00
Current Penalty: $0.00
Issuance Date: 01/21/2014
Nr Instances: 4
Nr Exposed: 20
Abatement Date: 02/14/2014
Gravity:
Report ID: 0213900
Contest Date:
Final Order: 02/07/2014
Related Event Code (REC):
Emphasis:
| Type | Latest Event | Event Date | Penalty | Abatement Due Date | Citation Type | Failure to Abate Inspection |
|---|---|---|---|---|---|---|
| Penalty | I: Informal Settlement | 02/07/2014 | $0.00 | 02/14/2014 | Other | |
| Penalty | Z: Issued | 01/21/2014 | $0.00 | 02/14/2014 | Other |
Text For Citation: 02 Item/Group: 004 Hazard:
29 CFR 1910.179(j)(3): Complete inspections of the crane was not being performed at intervals as generally defined in paragraph (j)(1)(ii)(b) of this section: a) Maintenance shop: Periodic inspections were not conducted on a one ton Coffing crane, on or about 7/23/13. b) Chlorine room: Periodic inspections were not conducted on a two ton Budgit crane, on or about 7/23/13. c) Furnace area H: Periodic inspections were not conducted on each of the two ton Budgit cranes, on or about 7/23/13. d) Furnace area M: Periodic inspections were not conducted on each of the two ton Budgit cranes, on or about 7/23/13.