Violation Detail
Standard Cited: 19100303 C03 I General.
Inspection Nr: 921325.015
Citation: 02004
Citation Type: Other
Abatement Status: Abatement Completed
Initial Penalty: $0.00
Current Penalty: $0.00
Issuance Date: 11/21/2013
Nr Instances: 1
Nr Exposed: 2
Abatement Date: 12/20/2013
Gravity:
Report ID: 0420600
Contest Date:
Final Order: 12/16/2013
Related Event Code (REC):
Emphasis:
| Type | Latest Event | Event Date | Penalty | Abatement Due Date | Citation Type | Failure to Abate Inspection |
|---|---|---|---|---|---|---|
| Penalty | I: Informal Settlement | 12/16/2013 | $0.00 | 12/20/2013 | Other | |
| Penalty | Z: Issued | 11/21/2013 | $0.00 | 12/04/2013 | Other |
Text For Citation: 02 Item/Group: 004 Hazard:
29 CFR 1910.303(c)(3)(i): All splices and joints and the free ends of conductors were not covered with an insulation equivalent to that of the conductors or with an insulating device identified for the purpose: a) for the establishment located at 2401 Airport Road Plant City (FL), where employees were using an altered electrical cord that was coming directly from an electrical panel to a Bridgeport Milling Machine for supplying power by splicing the power cord of the milling machine and taping the two connections together, on or about July 19th, 2013.
Translate