Violation Detail
Standard Cited: 19100119 J02 Process safety management of highly hazardous chemicals.
Inspection Nr: 663538.015
Citation: 02004
Citation Type: Serious
Abatement Status: Abatement Completed
Initial Penalty: $38,500.00
Current Penalty: $7,000.00
Issuance Date: 03/27/2013
Nr Instances: 1
Nr Exposed: 36
Abatement Date: 04/10/2013
Gravity: 10
Report ID: 0627700
Contest Date: 04/17/2013
Final Order: 10/27/2020
Related Event Code (REC):
Emphasis:
Type | Latest Event | Event Date | Penalty | Abatement Due Date | Citation Type | Failure to Abate Inspection |
---|---|---|---|---|---|---|
Penalty | R: Review Commission | 10/27/2020 | $7,000.00 | 04/10/2013 | Serious | |
Penalty | C: Contested | 04/19/2013 | $38,500.00 | 04/10/2013 | Repeat | |
Penalty | Z: Issued | 03/27/2013 | $38,500.00 | 04/10/2013 | Repeat |
Text For Citation: 02 Item/Group: 004 Hazard:
29 CFR 1910.119(j)(2): The employer did not establish and implement written procedures to maintain the on-going mechanical integrity of process equipment: The employer does not establish and implement written procedures to maintain the on-going mechanical integrity of process equipment. In the Zone 2/CAT Wickes Boiler Area the employer did not ensure written procedures were established and implemented for the testing and inspection of the Low Combustion Air Flow Fuel Gas Shut-off system safeguard. Employees were exposed to fire and explosion hazards from potential releases of fuel gas and other flammable liquids or gasses. WYNNEWOOD REFINING WAS PREVIOUSLY CITED FOR A VIOLATION OF THIS OCCUPATIONAL SAFETY AND HEALTH STANDARD OR ITS EQUIPVALENT STANDARD, 29 CFR 1910.119(j)(2), WHICH WAS CONTAINED IN OSHA INSPECTION NUMBER #309785459, CITATION NUMBER #1, Item# 10 AND WAS AFFIRMED AS FINAL ORDER ON AUGUST 4, 2008, WITH RESPECT TO A WORKPLACE LOCATED AT 906 S. POWELL, WYNNEWOOD OK 73098. Pursuant to 29 C.F.R. 1903.19, within ten (10) calendar days of the abatement date the employer must submit documentation showing it is in compliance with the standard, including describing the steps it is taking to ensure written procedures are established and implemented to maintain the on-going mechanical integrity of the process equipment.