Violation Detail
Standard Cited: 19100219 E03 I Mechanical power-transmission apparatus.
Inspection Nr: 302534912
Citation: 02004
Citation Type: Other
Abatement Status: X
Initial Penalty:
Current Penalty:
Issuance Date: 08/16/1999
Nr Instances: 11
Nr Exposed: 12
Abatement Date: 05/01/2000
Gravity: 01
Report ID: 0111700
Contest Date:
Final Order:
Related Event Code (REC):
Emphasis:
| Type | Latest Event | Event Date | Penalty | Abatement Due Date | Citation Type | Failure to Abate Inspection |
|---|---|---|---|---|---|---|
| Penalty | P: Petition to Mod Abatement | 10/12/1999 | 05/01/2000 | Other | ||
| Penalty | I: Informal Settlement | 09/10/1999 | 11/01/1999 | Other | ||
| Penalty | Z: Issued | 08/16/1999 | 09/20/1999 | Other |