Violation Detail
Standard Cited: 19100219 C02 I Mechanical power-transmission apparatus.
Inspection Nr: 1802527.015
Citation: 02004
Citation Type: Other
Abatement Status: Abatement Completed
Initial Penalty: $0.00
Current Penalty: $0.00
Issuance Date: 03/27/2025
Nr Instances: 1
Nr Exposed: 4
Abatement Date: 05/13/2025
Gravity:
Report ID: 0112000
Contest Date:
Final Order: 04/17/2025
Related Event Code (REC):
Emphasis:
| Type | Latest Event | Event Date | Penalty | Abatement Due Date | Citation Type | Failure to Abate Inspection |
|---|---|---|---|---|---|---|
| Penalty | I: Informal Settlement | 04/17/2025 | $0.00 | 05/13/2025 | Other | |
| Penalty | Z: Issued | 03/27/2025 | $0.00 | 05/13/2025 | Other |
Text For Citation: 02 Item/Group: 004 Hazard:
29 CFR 1910.219(c)(2)(i): All exposed part(s) of horizontal shafting seven (7) feet or less from floor or working platform were not protected by stationary casing(s) enclosing shafting completely or by trough(s) enclosing sides and top or sides and bottom of shafting: Cooler Tunnel: On, or about, February 5, 2025, a horizontal shaft provided at the start end of the cross-stacking conveyor was not provided with a guard.