Standard Cited: 19100303 G01 II General.
Inspection Nr: 1593249.015
Citation: 02004
Citation Type: Willful
Abatement Status: Abatement Completed
Initial Penalty: $136,736.00
Current Penalty: $136,736.00
Issuance Date: 10/26/2022
Nr Instances: 1
Nr Exposed: 4
Abatement Date: 11/22/2022
Gravity: 5
Report ID: 0418300
Contest Date: 10/28/2022
Final Order: 11/21/2024
Related Event Code (REC):
Emphasis:
Type | Latest Event | Event Date | Penalty | Abatement Due Date | Citation Type | Failure to Abate Inspection |
---|---|---|---|---|---|---|
Penalty | F: Formal Settlement | 11/21/2024 | $136,736.00 | 11/22/2022 | Willful | |
Penalty | C: Contested | 11/30/2022 | $136,736.00 | 11/22/2022 | Willful | |
Penalty | Z: Issued | 10/26/2022 | $136,736.00 | 11/22/2022 | Willful |
Text For Citation: 02 Item/Group: 004 Hazard:
29 CFR 1910.303(g)(1)(ii): The required working space about electric equipment rated 600 volts, nominal, or less to ground, was used for storage: a) The employer fails to ensure effective measures to prevent slip/trip, struck-by, fire, and electrical hazards as demonstrated on or about April 29, 2022, in front of the electrical panels in the back storage room in the back storage room, merchandise, cardboard boxes, U-boats, plastic bins, and other items were stored in front of the electrical panels. To abate this hazard, the employer must ensure that the area in front of electrical panels is not used for storage.