Violation Detail
Standard Cited: 19100147 C06 I The control of hazardous energy (lockout/tagout).
Inspection Nr: 1184785.015
Citation: 02004
Citation Type: Other
Abatement Date: 04/17/2019 2
Initial Penalty: $8,149.00
Current Penalty: $1,356.00
Issuance Date: 03/07/2017
Nr Instances: 1
Nr Exposed: 8
Related Event Code (REC):
Gravity:
Report ID: 0521400
Contest Date: 03/17/2017
Final Order: 11/30/2018
Emphasis:
Type | Latest Event | Event Date | Penalty | Abatement Due Date | Citation Type | Failure to Abate Inspection |
---|---|---|---|---|---|---|
Penalty | F: Formal Settlement | 11/30/2018 | $1,356.00 | 04/17/2019 | Other | |
Penalty | C: Contested | 03/21/2017 | $8,149.00 | 04/13/2017 | Serious | |
Penalty | Z: Issued | 03/07/2017 | $8,149.00 | 04/13/2017 | Serious |
Text For Citation: 02 Item/Group: 004 Hazard:
29 CFR 1910.147(c)(6)(i): The employer did not conduct an annual or more frequent inspection of the energy control procedure to ensure that the procedure and requirements of this standard were followed: MES department, MES 1, MES 2, MES 3 - on or about October 18, 2016, the employer did not inspect hazardous energy control (lockout) procedures periodically (at least once per year) to ensure they were adequate and being followed in accordance with the requirements of 29 CFR 1910.147. Operators assigned to perform setup (servicing) on energized equipment were exposed to machine struck-by and caught-in hazards likely to result in serious injury. Abatement documentation is required for this item in accordance with the requirements of 29 CFR 1903.19(d).