Powered by GoogleTranslate

Violation Detail

Standard Cited: 19260501 B13 Duty to have fall protection.

This violation item has been deleted.

Inspection Nr: 943345.015

Citation: 02003

Citation Type: Repeat

Abatement Status: Abatement Completed

Initial Penalty: $5,600.00

Current Penalty: $0.00

Issuance Date: 11/06/2013

Nr Instances: 2

Nr Exposed: 2

Abatement Date: 11/13/2013

Gravity: 10

Report ID: 0316100

Contest Date:

Final Order: 11/13/2013

Related Event Code (REC):

Emphasis:


Penalty and Failure to Abate Event History
Type Latest Event Event Date Penalty Abatement Due Date Citation Type Failure to Abate Inspection
Penalty I: Informal Settlement 11/13/2013 $0.00 11/13/2013 Repeat  
Penalty Z: Issued 11/06/2013 $5,600.00 11/13/2013 Repeat  

Text For Citation: 02 Item/Group: 003 Hazard:

29 CFR 1926.501(b)(13): Each employee(s) engaged in residential construction activities 6 feet (1.8 m) or more above lower levels were not protected by guardrail systems, safety net system, or personal fall arrest system, nor were employee(s) provided with an alternative fall protection measure under another provision of paragraph 1926.501 (b): a) Second Floor, New Addition - Employees were observed standing at the edge of an open deck while dropping demolition debris to the ground, and exposed to a 15 foot, 7 inch fall hazard, on or about 10/18/2013. b) Second Floor, Existing Section - A carpenter was observed cutting a 2X4 near a floor hole that measured 40 inches wide, 14 feet, 4 inches in length that was used as a ladder opening and exposed to a 10 feet, 3 inch fall hazard, on or about 10/18/2013. AJP Builders, LLC was previously cited for a violation of this occupational safety and health standard or its equivalent standard 29 CFR 1926.501(b)(13) which was contained in OSHA inspection number 921047, citation number 1, item number 3, and was affirmed as a final order on 09/10/13, with respect to a workplace located at 3812 25th Place, NE Washington DC 20018. Abatement certification and documentation required within 10 days after abatement date. The certification shall include a statement that abatement is complete, the date and method of abatement, and state that employees and their representatives were informed of this abatement. Abatement documentation shall include documents demonstrating that abatement is complete, such as evidence of the purchase or repair of equipment, photographic or video evidence of abatement or other written records.

Thank You for Visiting Our Website

You are exiting the Department of Labor's Web server.

The Department of Labor does not endorse, takes no responsibility for, and exercises no control over the linked organization or its views, or contents, nor does it vouch for the accuracy or accessibility of the information contained on the destination server. The Department of Labor also cannot authorize the use of copyrighted materials contained in linked Web sites. Users must request such authorization from the sponsor of the linked Web site. Thank you for visiting our site. Please click the button below to continue.