Violation Detail
Standard Cited: 19100219 E03 I Mechanical power-transmission apparatus.
Inspection Nr: 894302.015
Citation: 02003
Citation Type: Other
Abatement Date: 06/20/2013 2
Initial Penalty: $0.00
Current Penalty: $0.00
Issuance Date: 05/16/2013
Nr Instances: 1
Nr Exposed: 10
Related Event Code (REC):
Gravity:
Report ID: 0830500
Contest Date:
Final Order: 06/21/2013
Emphasis:
Type | Latest Event | Event Date | Penalty | Abatement Due Date | Citation Type | Failure to Abate Inspection |
---|---|---|---|---|---|---|
Penalty | I: Informal Settlement | 06/21/2013 | $0.00 | 06/20/2013 | Other | |
Penalty | Z: Issued | 05/16/2013 | $0.00 | 06/20/2013 | Other |
Text For Citation: 02 Item/Group: 003 Hazard:
29 CFR 1910.219(e)(3)(i): Vertical or inclined belt(s) were not enclosed by guard(s) conforming to the requirements specified at 29 CFR 1910.219(m) and (o): (a) Weiser Engineering/Mile High Precision Inc. at 10901 Irma Drive, Northglenn, CO: On and before March 7, 2013 the employer did not ensure that the belt of the drive motor on the Shear was guarded. The belt is located approximately three-feet from the operators feet. This condition exposed employees to the hazard of being caught in ingoing nip points.