Violation Detail
Standard Cited: 19100253 B05 II I Oxygen-fuel gas welding and cutting.
Inspection Nr: 280761.015
Citation: 02003
Citation Type: Other
Abatement Status: Corrected During Inspection
Initial Penalty: $0.00
Current Penalty: $0.00
Issuance Date: 08/01/2012
Nr Instances: 1
Nr Exposed: 3
Abatement Date:
Gravity:
Report ID: 1032500
Contest Date:
Final Order: 08/22/2012
Related Event Code (REC): C
Emphasis:
| Type | Latest Event | Event Date | Penalty | Abatement Due Date | Citation Type | Failure to Abate Inspection |
|---|---|---|---|---|---|---|
| Penalty | I: Informal Settlement | 08/22/2012 | $0.00 | Other | ||
| Penalty | Z: Issued | 08/01/2012 | $0.00 | Other |
Text For Citation: 02 Item/Group: 003 Hazard:
29 CFR 1910.253(b)(5)(ii)(I): Cylinders were not kept far enough away from the actual welding or cutting operation so that sparks, hot slag, or flame would not reach them: (a) In the welding shop: On or about March 13, 2012, and at times prior thereto, the acetylene bottles were stored in the west welding bay near the area where trailer repairs occurred. Note: Abatement certification is not required for this item.
Translate