Standard Cited: 19100305 G01 IV A Wiring methods, components, and equipment for general use.
Inspection Nr: 1734779.015
Citation: 02003
Citation Type: Other
Abatement Status: Abatement Completed
Initial Penalty: $0.00
Current Penalty: $0.00
Issuance Date: 05/24/2024
Nr Instances: 1
Nr Exposed: 12
Abatement Date: 12/18/2024
Gravity:
Report ID: 0317700
Contest Date: 06/18/2024
Final Order: 11/18/2024
Related Event Code (REC):
Emphasis:
Type | Latest Event | Event Date | Penalty | Abatement Due Date | Citation Type | Failure to Abate Inspection |
---|---|---|---|---|---|---|
Penalty | F: Formal Settlement | 11/18/2024 | $0.00 | 12/18/2024 | Other | |
Penalty | C: Contested | 06/21/2024 | $0.00 | 06/21/2024 | Other | |
Penalty | Z: Issued | 05/24/2024 | $0.00 | 06/21/2024 | Other |
Text For Citation: 02 Item/Group: 003 Hazard:
29 CFR 1910.305(g)(1)(iv)(A): Flexible cords and/or cables were used as a substitute for the fixed wiring of a structure: a) Main Shop: On or about March 14, 2024, employees were exposed to shock hazards due to retractable flexible cords being used as a s substitute for fixed wiring. Abatement certification required.