Violation Detail
Standard Cited: 19100119 J04 II Process safety management of highly hazardous chemicals.
Inspection Nr: 1613868.015
Citation: 02003
Citation Type: Other
Abatement Status: Abatement Completed
Initial Penalty: $14,502.00
Current Penalty: $0.00
Issuance Date: 12/21/2022
Nr Instances: 1
Nr Exposed: 10
Abatement Date: 05/01/2023
Gravity: 10
Report ID: 0627510
Contest Date:
Final Order: 02/22/2023
Related Event Code (REC):
Emphasis:
Type | Latest Event | Event Date | Penalty | Abatement Due Date | Citation Type | Failure to Abate Inspection |
---|---|---|---|---|---|---|
Penalty | I: Informal Settlement | 02/22/2023 | $0.00 | 05/01/2023 | Other | |
Penalty | Z: Issued | 12/21/2022 | $14,502.00 | 02/13/2023 | Serious |
Text For Citation: 02 Item/Group: 003 Hazard:
29 CFR 1910.119(d)(3): Information pertaining to the equipment in the process. On or about August 9, 2022, the employer did not ensure that written process safety information for equipment in the process included the documentation of appropriate responses to inspector recommendations related to CML placement for the HF Alky Depropanizer Column T-011. The Employer will develop and implement its Deficiency Resolution for Fixed Equipment procedure which will include instructions and requirements for documenting rejected inspection recommendations. The employer will ensure that the BSR Fixed Equipment Inspection Team receive training on this procedure. Abatement due date will be 30 April 2023 and the employer will submit verification of abatement within 10 calendar days of the abatement due date.