Violation Detail
Standard Cited: 19100147 C06 I The control of hazardous energy (lockout/tagout).
Inspection Nr: 1142594.015
Citation: 02003
Citation Type: Other
Abatement Status: Abatement Completed
Initial Penalty: $0.00
Current Penalty: $0.00
Issuance Date: 07/12/2016
Nr Instances: 1
Nr Exposed: 20
Abatement Date: 08/26/2016
Gravity:
Report ID: 0112000
Contest Date:
Final Order: 08/02/2016
Related Event Code (REC):
Emphasis:
Type | Latest Event | Event Date | Penalty | Abatement Due Date | Citation Type | Failure to Abate Inspection |
---|---|---|---|---|---|---|
Penalty | I: Informal Settlement | 08/02/2016 | $0.00 | 08/26/2016 | Other | |
Penalty | Z: Issued | 07/12/2016 | $0.00 | 08/26/2016 | Other |
Text For Citation: 02 Item/Group: 003 Hazard:
29 CFR 1910.147(c)(6)(i): The employer did not conduct a periodic inspection of the energy control procedure at least annually to ensure that the procedure and the requirement of this standard were being followed: Plant: On, or about, May 24, 2016, the company had not conducted an annual review of the lockout procedures provided for equipment in the plant.