Violation Detail
Standard Cited: 19100265 C04 IV Sawmills.
Inspection Nr: 1132246.015
Citation: 02002A
Citation Type: Willful
Abatement Date: 09/15/2016 4
Initial Penalty: $47,032.00
Current Penalty: $15,500.00
Issuance Date: 09/02/2016
Nr Instances: 1
Nr Exposed: 13
Related Event Code (REC):
Gravity: 5
Report ID: 0316400
Contest Date: 09/27/2016
Final Order: 06/10/2017
Emphasis:
Type | Latest Event | Event Date | Penalty | Abatement Due Date | Citation Type | Failure to Abate Inspection |
---|---|---|---|---|---|---|
Penalty | F: Formal Settlement | 06/10/2017 | $15,500.00 | 09/15/2016 | Willful | |
Penalty | C: Contested | 09/30/2016 | $47,032.00 | 09/15/2016 | Willful | |
Penalty | Z: Issued | 09/02/2016 | $47,032.00 | 09/15/2016 | Willful |
Text For Citation: 02 Item/Group: 002A Hazard:
29 CFR 1910.265(c)(4)(iv): The employer did not ensure all elevated walks, runways, or platforms, if 4 feet or more from the floor level, were provided with a standard railing: (a) Sawmill: The elevated sawmill, measuring up to 6ft. 8in. to the ground, is not provided with a standard railing on road side back of the mill all the way around the mill to stairs entering the head saw carriage area on side opposite the road. This violation was most recently determined on March 9, 2016.