Violation Detail
Standard Cited: 19100022 A02 General requirements.
Inspection Nr: 959401.015
Citation: 02002
Citation Type: Other
Abatement Status: Not Completed - AD Discretion
Initial Penalty: $0.00
Current Penalty: $0.00
Issuance Date: 03/28/2014
Nr Instances: 1
Nr Exposed: 2
Abatement Date: 04/23/2014
Gravity:
Report ID: 0316700
Contest Date:
Final Order: 04/22/2014
Related Event Code (REC): C
Emphasis:
Type | Latest Event | Event Date | Penalty | Abatement Due Date | Citation Type | Failure to Abate Inspection |
---|---|---|---|---|---|---|
Penalty | Z: Issued | 03/28/2014 | $0.00 | 04/23/2014 | Other |
Text For Citation: 02 Item/Group: 002 Hazard:
29 CFR 1910.22(a)(2): Floor(s) of workroom(s) were not maintained in a clean and, so far as possible, a dry condition: a) 2nd floor machine shop - Employees working in the second floor machine shop were exposed to slipping hazards from rain puddles, on or about February 26, 2014. Abatement certification required within 10 days after abatement date. The certification shall include a statement that abatement is complete, date and method of abatement, and states employees and their representatives were informed of this abatement.