Standard Cited: 19100119 F03 Process safety management of highly hazardous chemicals.
Inspection Nr: 906171.015
Citation: 02002
Citation Type: Other
Abatement Status: Abatement Completed
Initial Penalty: $0.00
Current Penalty: $0.00
Issuance Date: 10/08/2013
Nr Instances: 15
Nr Exposed: 100
Abatement Date: 11/26/2013
Gravity:
Report ID: 0523400
Contest Date:
Final Order: 10/28/2013
Related Event Code (REC): R
Emphasis:
| Type | Latest Event | Event Date | Penalty | Abatement Due Date | Citation Type | Failure to Abate Inspection |
|---|---|---|---|---|---|---|
| Penalty | I: Informal Settlement | 10/28/2013 | $0.00 | 11/26/2013 | Other | |
| Penalty | Z: Issued | 10/08/2013 | $0.00 | 11/26/2013 | Other |
Text For Citation: 02 Item/Group: 002 Hazard:
29 CFR 1910.119(f)(3): The employer did not annually certify that operating procedures were current and accurate. Operating procedures for ammonia refrigeration system equipment and processes were not certified annually as being current and accurate for the following equipment, but not limited to: (a) Overall Ammonia System Operations procedure was not certified annually as being current and accurate. (b) Oil Draining procedure was not certified annually as being current and accurate. (c) Ammonia Charging procedure was not certified annually as being current and accurate. (d) High Stage TS Cooled Screw Compressors procedure was not certified annually as being current and accurate. (e) High Stage Ll Cooled Screw Compressors procedure was not certified annually as being current and accurate. (f) High Stage Reciprocating Compressors procedure was not certified annually as being current and accurate. (g) Low Stage Screw Compressor was not certified annually as being current and accurate. (h) Low Stage Reciprocating Compressor was not certified annually as being current and accurate. (i) Evaporative Condensers procedure was not certified annually as being current and accurate. (j) High Pressure Receiver procedure was not certified annually as being current and accurate. (k) Flooded S&T Water Chiller with oil pot was not certified annually as being current and accurate. (l) Flooded S&T Glycol Chiller without oil pot was not certified annually as being current and accurate. (m) Blast Freezer Units procedure was not certified annually as being current and accurate. (n) Evapco Makeup Air Units procedure was not certified annually as being current and accurate. (o) Krack Makeup Air Unit procedure was not certified annually as being current and accurate.