Violation Detail
Standard Cited: 19100124 J02 I
Inspection Nr: 1737659.015
Citation: 02002
Citation Type: Other
Abatement Status: Abatement Completed
Initial Penalty: $0.00
Current Penalty: $0.00
Issuance Date: 08/28/2024
Nr Instances: 1
Nr Exposed: 5
Abatement Date: 09/24/2024
Gravity:
Report ID: 0336000
Contest Date:
Final Order: 09/18/2024
Related Event Code (REC):
Emphasis:
Type | Latest Event | Event Date | Penalty | Abatement Due Date | Citation Type | Failure to Abate Inspection |
---|---|---|---|---|---|---|
Penalty | I: Informal Settlement | 09/18/2024 | $0.00 | 09/24/2024 | Other | |
Penalty | Z: Issued | 08/28/2024 | $0.00 | 09/24/2024 | Other |
Text For Citation: 02 Item/Group: 002 Hazard:
29 CFR 1910.124(j)(2)(i): The employer did not ensure airflow was adequate at least quarterly during operation: a.) Alpha Precision Group, LLC dba Alpha Sintered Metals, Kohler room, on or about 3/27/24 and at times prior thereto: Regular testing and inspections of the ventilation system were not being conducted to ensure equipment was operating properly and no hazardous conditions existed. ABATEMENT CERTIFICATION REQUIRED: Abatement certification is required within 10 days after the abatement date noted on the citation (see below). This certification shall include a statement that abatement is complete, the date abatement was completed, method of abatement, and state that employees and their representatives were informed of this abatement.