Violation Detail
Standard Cited: 19100305 G01 IV A Wiring methods, components, and equipment for general use.
Inspection Nr: 1725822.015
Citation: 02002
Citation Type: Other
Abatement Status: Corrected During Inspection
Initial Penalty: $440.00
Current Penalty: $264.00
Issuance Date: 02/09/2024
Nr Instances: 2
Nr Exposed: 5
Abatement Date:
Gravity:
Report ID: 0636900
Contest Date:
Final Order: 02/22/2024
Related Event Code (REC):
Emphasis:
| Type | Latest Event | Event Date | Penalty | Abatement Due Date | Citation Type | Failure to Abate Inspection |
|---|---|---|---|---|---|---|
| Penalty | I: Informal Settlement | 02/22/2024 | $264.00 | Other | ||
| Penalty | Z: Issued | 02/09/2024 | $440.00 | Other |
Text For Citation: 02 Item/Group: 002 Hazard:
29 CFR 1910.305(g)(1)(iv)(A): Flexible cords and/or cables were used as a substitute for the fixed wiring of a structure. On or about February 5, 2024, and times prior thereto, extension cords, zip tied and wrapped around metal conduit, was used as permanent wiring to energize the machines, exposing employees to electrical shock hazards. a) The mistaway located on top of the Infinity machine was plugged into an extension cord wrapped and zip tied to conduit, b) At the Fadal machine an extension cord zipped tied and wrapped around conduit was used to energize a fan and computer.