Violation Detail
Standard Cited: 19100147 C06 I The control of hazardous energy (lockout/tagout).
Inspection Nr: 1721548.015
Citation: 02002
Citation Type: Other
Abatement Status: Abatement Completed
Initial Penalty: $0.00
Current Penalty: $0.00
Issuance Date: 05/22/2024
Nr Instances: 1
Nr Exposed: 20
Abatement Date: 09/27/2024
Gravity:
Report ID: 0523900
Contest Date:
Final Order: 06/18/2024
Related Event Code (REC):
Emphasis:
Type | Latest Event | Event Date | Penalty | Abatement Due Date | Citation Type | Failure to Abate Inspection |
---|---|---|---|---|---|---|
Penalty | I: Informal Settlement | 06/18/2024 | $0.00 | 09/27/2024 | Other | |
Penalty | Z: Issued | 05/22/2024 | $0.00 | 06/21/2024 | Other |
Text For Citation: 02 Item/Group: 002 Hazard:
29 CFR 1910.147(c)(6)(i): The employer did not conduct a periodic inspection of the energy control procedure at least annually to ensure that the procedure and the requirements of this standard were being followed: (a) Throughout the production area; On or about January 17, 2024, and dates prior, written energy isolation (LOTO) procedures were not evaluated annually for equipment including, but not limited to the finger jointer table, finger joint crowder, RF tunnel, Newman Machine Company planer, stacker, and inter-related conveyances.