Violation Detail
Standard Cited: 19260651 B03 Specific Excavation Requirements.
Inspection Nr: 1684502.015
Citation: 02002
Citation Type: Willful
Abatement Status: Abatement Completed
Initial Penalty: $137,508.00
Current Penalty: $25,469.00
Issuance Date: 12/12/2023
Nr Instances: 10
Nr Exposed: 4
Abatement Date: 12/20/2023
Gravity: 10
Report ID: 0111100
Contest Date:
Final Order: 12/28/2023
Related Event Code (REC): R
Emphasis:
Type | Latest Event | Event Date | Penalty | Abatement Due Date | Citation Type | Failure to Abate Inspection |
---|---|---|---|---|---|---|
Penalty | I: Informal Settlement | 12/28/2023 | $25,469.00 | 12/20/2023 | Willful | |
Penalty | Z: Issued | 12/12/2023 | $137,508.00 | 12/20/2023 | Willful |
Text For Citation: 02 Item/Group: 002 Hazard:
29 CFR 1926.651(b)(3): When excavation operations approached the estimated location of underground installations, the exact location of the installations was not determined by safe and acceptable means: Neptune Drive, Brunswick- The employer did not use a safe and acceptable means of to identify the location of the a 2 inch natural gas line during soil removal around ten trenches resulting in significant damage to the line from an excavator and shovel strikes over the course of three days.