Violation Detail
Standard Cited: 19100119 D03 I B Process safety management of highly hazardous chemicals.
Inspection Nr: 1459787.015
Citation: 02002
Citation Type: Other
Abatement Status: Abatement Completed
Initial Penalty: $1,082.00
Current Penalty: $1,082.00
Issuance Date: 07/22/2020
Nr Instances: 3
Nr Exposed: 5
Abatement Date: 09/30/2020
Gravity:
Report ID: 0728500
Contest Date:
Final Order: 08/17/2020
Related Event Code (REC):
Emphasis:
| Type | Latest Event | Event Date | Penalty | Abatement Due Date | Citation Type | Failure to Abate Inspection |
|---|---|---|---|---|---|---|
| Penalty | I: Informal Settlement | 08/17/2020 | $1,082.00 | 09/30/2020 | Other | |
| Penalty | Z: Issued | 07/22/2020 | $1,082.00 | Other |
Text For Citation: 02 Item/Group: 002 Hazard:
29 CFR 1910.119(d)(3)(i)(B): The employer's piping and instrument diagrams were not accurate and did not represent equipment that was existing and was part of the process. At a worksite located at 17562 Gum Rd, Carthage, MO: Employees were exposed to fire and explosion hazards. The employer failed to protect employees in that the Piping and Instrumentation Diagram (PIDC-CPPR-3148-11) developed for the system is not accurate, complete, and up-to-date for the covered process equipment associated with the synthesis of various chemical products using AN and SN prills, K37, and 7019 as the reagents associated with the Chub Dry Ingredient Transfer process equipment. a) P&ID was not accurate for as a hopper labeled FD-002 was misidentified when the legend identifies that same hopper as F-002.