Powered by GoogleTranslate

Violation Detail

Standard Cited: 19100303 B01 IV General.

This violation item has been deleted.

Inspection Nr: 1425480.015

Citation: 02002

Citation Type: Other

Abatement Status: Corrected During Inspection

Initial Penalty: $904.00

Current Penalty: $0.00

Issuance Date: 10/11/2019

Nr Instances: 1

Nr Exposed: 1

Abatement Date:

Gravity:

Report ID: 0419400

Contest Date:

Final Order: 11/12/2019

Related Event Code (REC): C

Emphasis:


Penalty and Failure to Abate Event History
Type Latest Event Event Date Penalty Abatement Due Date Citation Type Failure to Abate Inspection
Penalty I: Informal Settlement 11/12/2019 $0.00   Other  
Penalty Z: Issued 10/11/2019 $904.00   Other  

Text For Citation: 02 Item/Group: 002 Hazard:

29 CFR 1910.303(b)(1)(iv): Electric equipment was not free from recognized hazards that are likely to cause death or serious physical harm to employees such as damaged insulation: (a) Press 9 - On or about August 21, 2019 the employer did not ensure that the outer insulation protected the 24 volt internal wires of a flexible cord connected to the control unit were intact, exposing the employee to an electrical shock when operating the press feed and straightener.

Thank You for Visiting Our Website

You are exiting the Department of Labor's Web server.

The Department of Labor does not endorse, takes no responsibility for, and exercises no control over the linked organization or its views, or contents, nor does it vouch for the accuracy or accessibility of the information contained on the destination server. The Department of Labor also cannot authorize the use of copyrighted materials contained in linked Web sites. Users must request such authorization from the sponsor of the linked Web site. Thank you for visiting our site. Please click the button below to continue.