Violation Detail
Standard Cited: 19260451 F06 General requirements.
Inspection Nr: 1247161.015
Citation: 02002
Citation Type: Willful
Abatement Status: Not Completed - Worksite Changed
Initial Penalty: $28,454.00
Current Penalty: $18,495.00
Issuance Date: 01/09/2018
Nr Instances: 1
Nr Exposed: 2
Abatement Date: 01/22/2018
Gravity: 10
Report ID: 0317000
Contest Date:
Final Order: 05/24/2018
Related Event Code (REC):
Emphasis:
Type | Latest Event | Event Date | Penalty | Abatement Due Date | Citation Type | Failure to Abate Inspection |
---|---|---|---|---|---|---|
Penalty | I: Informal Settlement | 05/24/2018 | $18,495.00 | 01/22/2018 | Willful | |
Penalty | Z: Issued | 01/09/2018 | $28,454.00 | 01/22/2018 | Willful |
Text For Citation: 02 Item/Group: 002 Hazard:
29 CFR 1926.451(f)(6): Scaffolds were erected, used, dismantled, altered, or moved such that they or any conductive material handled on them might come closer than 10 ft to exposed and energized power lines: a) Jobsite: The employer did not ensure that a tubular welded scaffold was erected closer than 10 feet from a 13.2kV live electrical power line. Condition was noted on or about 12 Jul 2017.