Violation Detail
Standard Cited: 19100036 G02 Design and construction requirements for exit routes.
Inspection Nr: 1131470.015
Citation: 02002
Citation Type: Serious
Abatement Status: Abatement Completed
Initial Penalty: $5,880.00
Current Penalty: $5,880.00
Issuance Date: 09/02/2016
Nr Instances: 1
Nr Exposed: 21
Abatement Date: 10/21/2016
Gravity: 1
Report ID: 0316700
Contest Date: 09/12/2016
Final Order: 11/08/2022
Related Event Code (REC):
Emphasis:
Type | Latest Event | Event Date | Penalty | Abatement Due Date | Citation Type | Failure to Abate Inspection |
---|---|---|---|---|---|---|
Penalty | 2: Appeals Court | 11/08/2022 | $5,880.00 | 10/21/2016 | Serious | |
Penalty | C: Contested | 09/13/2016 | $5,880.00 | 10/21/2016 | Serious | |
Penalty | Z: Issued | 09/02/2016 | $5,880.00 | 10/21/2016 | Serious |
Text For Citation: 02 Item/Group: 002 Hazard:
29 CFR 1910.36(g)(2): Exit access(es) were not at least 28 inches (71.1 cm) wide at all points: a) Central Access for the Evisceration Room Line - On or about July 6, 2016, the exit route for employees working at the evisceration line was only 21 inches wide between the chicken hanger conveyer and the salted chicken conveyer. Abatement certification required within 10 days after abatement date. The certification shall include a statement that abatement is complete, date and method of abatement, and states employees and their representatives were informed of this abatement.