Standard Cited: 19100147 C06 I The control of hazardous energy (lockout/tagout).
Inspection Nr: 1046874.015
Citation: 02002
Citation Type: Other
Abatement Date: 10/09/2015 2
Initial Penalty: $0.00
Current Penalty: $0.00
Issuance Date: 08/24/2015
Nr Instances: 1
Nr Exposed: 34
Related Event Code (REC):
Gravity:
Report ID: 0419700
Contest Date:
Final Order: 09/18/2015
Emphasis:
Type | Latest Event | Event Date | Penalty | Abatement Due Date | Citation Type | Failure to Abate Inspection |
---|---|---|---|---|---|---|
Penalty | I: Informal Settlement | 09/18/2015 | $0.00 | 10/09/2015 | Other | |
Penalty | Z: Issued | 08/24/2015 | $0.00 | 10/09/2015 | Other |
Text For Citation: 02 Item/Group: 002 Hazard:
29 CFR 1910.147(c)(6)(i): The employer did not conduct an annual or more frequent inspection of the energy control procedure to ensure that the procedure and requirements of this standard were followed: a. On or about March 17, 2015, Plant Wide - The employer did not conduct an annual or more frequent inspection of the facility's energy control procedure to ensure that it was properly implemented during the repair and service work on equipment, to include but not limited to; wire stranding machines, wire drawing machines, re-reeling machines, an over-head crane and forklifts, exposing employees to struck-by, caught-in, crushing, and electrical shock hazards.