Violation Detail
Standard Cited: 19100147 F03 I The control of hazardous energy (lockout/tagout).
Inspection Nr: 1562262.015
Citation: 02001B
Citation Type: Repeat
Abatement Status: Abatement Completed
Initial Penalty: $0.00
Current Penalty: $0.00
Issuance Date: 04/22/2022
Nr Instances: 1
Nr Exposed: 2
Abatement Date: 07/03/2023
Gravity: 10
Report ID: 0521700
Contest Date: 05/13/2022
Final Order: 12/21/2023
Related Event Code (REC): R
Emphasis:
Type | Latest Event | Event Date | Penalty | Abatement Due Date | Citation Type | Failure to Abate Inspection |
---|---|---|---|---|---|---|
Penalty | F: Formal Settlement | 12/21/2023 | $0.00 | 07/03/2023 | Repeat | |
Penalty | C: Contested | 05/13/2022 | $0.00 | 05/18/2022 | Willful | |
Penalty | Z: Issued | 04/22/2022 | $0.00 | 05/18/2022 | Willful |
Text For Citation: 02 Item/Group: 001B Hazard:
29 CFR 1910.147(f)(3)(i): A procedure was not utilized to afford the employees a level of protection equivalent to that provided by the implementation of a personal lockout or tagout device when servicing and/or maintenance was performed by a crew, craft, department or other group: a) Phase 4, Production Line 16 - On or about October 30, 2021, the employer failed to ensure that a procedure was utilized to afford the Changeover and Maintenance Mechanics a level of protection equivalent to that provided by the implementation of a personal lockout or tagout device when servicing and maintenance was performed by both employees on the RP-16 Kliklok Vari-Straight Topload Carton Closer, serial no. VS-198/A0338. The employees were exposed to machine hazards associated with moving parts and in-going nip points. The employees performing the work did not use group lockout.