Violation Detail
Standard Cited: 19100119 D03 I B Process safety management of highly hazardous chemicals.
Inspection Nr: 908161.015
Citation: 02001
Citation Type: Serious
Abatement Date: 12/11/2013 2
Initial Penalty: $38,500.00
Current Penalty: $7,000.00
Issuance Date: 11/21/2013
Nr Instances: 5
Nr Exposed: 18
Related Event Code (REC):
Gravity: 10
Report ID: 0626300
Contest Date: 12/10/2013
Final Order: 07/23/2014
Emphasis:
Type | Latest Event | Event Date | Penalty | Abatement Due Date | Citation Type | Failure to Abate Inspection |
---|---|---|---|---|---|---|
Penalty | C: Contested | 03/16/2015 | $38,500.00 | 12/11/2013 | Repeat | |
Penalty | F: Formal Settlement | 07/23/2014 | $7,000.00 | 12/11/2013 | Serious | |
Penalty | Z: Issued | 11/21/2013 | $38,500.00 | 12/11/2013 | Repeat |
Text For Citation: 02 Item/Group: 001 Hazard:
29 CFR 1910.119(d)(3)(i)(B): The employer's piping and instrument diagrams were not accurate and did not include process safety information that provided specific identification of equipment that is part of the process: The employer does not ensure that piping and instrument diagrams (P&IDs) were accurate and include process safety information pertaining to equipment. This violation occurred on or about May 23, 2013 and at times prior thereto in the Naphtha Hydrotreater (unit 30), Saturated Gas (unit 60), and Storage and Blending(unit 01) units where employees were exposed to inhalation, fire, and explosion hazards from potential releases of hazardous materials without ensure P&IDs were accurate and included process safety information (PSI) for the following instances. c. P&ID (DK-60-0-0002L, Rev. 16), Sponge Oil Absorber, by pass line for a lean oil air cooler (60-E-30) from the control valve (FV-002) to a lean oil water cooler (60-E-5) does not exist in the field.