Violation Detail
Standard Cited: 19100036 D01 Design and construction requirements for exit routes.
Inspection Nr: 893753.015
Citation: 02001
Citation Type: Serious
Abatement Date: 09/25/2013 2
Initial Penalty: $35,000.00
Current Penalty: $7,000.00
Issuance Date: 09/05/2013
Nr Instances: 1
Nr Exposed: 3
Related Event Code (REC): A
Gravity: 10
Report ID: 0521400
Contest Date: 09/26/2013
Final Order: 10/23/2014
Emphasis:
Type | Latest Event | Event Date | Penalty | Abatement Due Date | Citation Type | Failure to Abate Inspection |
---|---|---|---|---|---|---|
Penalty | F: Formal Settlement | 10/23/2014 | $7,000.00 | 09/25/2013 | Serious | |
Penalty | C: Contested | 11/18/2013 | $35,000.00 | 09/25/2013 | Willful | |
Penalty | Z: Issued | 09/05/2013 | $35,000.00 | 09/25/2013 | Willful |
Text For Citation: 02 Item/Group: 001 Hazard:
29 CFR 1910.36(d)(1): Employee(s) were not able to open an exit route door from the inside at all times without keys, tools, or special knowledge: On or about March 6, 2013, employees at Fox Valley Systems, Inc. were not able to open the exit door from the conveyor room (conveyor alley) from the inside at all times without keys, tools, or special knowledge. The door was locked from the outside. DOCUMENTATION AND CERTIFICATION ARE REQUIRED FOR THIS ITEM.