Powered by GoogleTranslate

Violation Detail

Standard Cited: 19260416 A01 General requirements.

Inspection Nr: 777302.015

Citation: 02001

Citation Type: Repeat

Abatement Status: Abatement Completed

Initial Penalty: $69,300.00

Current Penalty: $53,000.00

Issuance Date: 05/31/2013

Nr Instances: 6

Nr Exposed: 7

Abatement Date: 06/03/2013

Gravity: 10

Report ID: 0214700

Contest Date: 06/17/2013

Final Order: 01/21/2015

Related Event Code (REC):

Emphasis:


Penalty and Failure to Abate Event History
Type Latest Event Event Date Penalty Abatement Due Date Citation Type Failure to Abate Inspection
Penalty F: Formal Settlement 01/21/2015 $53,000.00 06/03/2013 Repeat  
Penalty C: Contested 06/21/2013 $69,300.00 06/03/2013 Willful  
Penalty Z: Issued 05/31/2013 $69,300.00 06/03/2013 Willful  

Text For Citation: 02 Item/Group: 001 Hazard:

29 CFR 1926.416(a)(1): Employees were permitted to work in proximity to electric power circuits and were not protected against electric shock by de-energizing and grounding the circuits or effectively guarding the circuits by insulation or other means: Instances (a) thru (d) are related to the overhead, 3-phase primary and secondary power lines and transformers, which were energized with 13,200 volts (13 kV) phase to phase. The overhead power lines run north and south, along the west side of Fourth Street with respect to the building under construction at 14 Brooklyn Avenue. (a) Worksite, north and east sides of building, third floor - Employees that installed the Engineered Fall Protection System along the north and east sides of the third floor worked directly below the overhead primary power line, which was approximately 3 feet above their heads. The primary power lines were energized with 7,620 volts (7.5 kV) phase to ground, on December 3, 2012. (b) Worksite, north and east sides of building, third floor - Employees constructed the masonry block wall directly below the overhead primary power line, which was energized with 7,620 volts (7.5 Kv) phase to ground. At times the employees were working approximately 12 inches below the power line, on or about December 4, 2012. (c) Worksite, northeast corner of building, third floor - Employees constructed the masonry block wall between the overhead primary power lines and near the secondary power lines. The primary power lines were energized with 13,200 volts (13 Kv) phase to phase. The secondary power lines were energized with 120 - 240 volts phase to ground. At times, employees were working approximately 4 inches from the primary power lines and approximately 14 inches from the secondary power lines, on or about December 5, 2012. (d) Worksite, north side of building, third floor - Employees constructed the masonry block wall around an overhead primary power line, which was energized with 7,620 volts (7.5 Kv) phase to ground. At times the employees were working approximately 4 inches from the power line, on or about December 5, 2012. Note: In addition to abatement certification, the employer is required to submit abatement documentation for this item in accordance with 29 CFR 1903.19.

Thank You for Visiting Our Website

You are exiting the Department of Labor's Web server.

The Department of Labor does not endorse, takes no responsibility for, and exercises no control over the linked organization or its views, or contents, nor does it vouch for the accuracy or accessibility of the information contained on the destination server. The Department of Labor also cannot authorize the use of copyrighted materials contained in linked Web sites. Users must request such authorization from the sponsor of the linked Web site. Thank you for visiting our site. Please click the button below to continue.

Close