Violation Detail
Standard Cited: 6A0001 General Duty Clause
Inspection Nr: 313368375
Citation: 02001
Citation Type: Other
Abatement Status: I
Initial Penalty: $650.00
Current Penalty: $455.00
Issuance Date: 07/22/2010
Nr Instances: 1
Nr Exposed: 1
Abatement Date: 07/27/2010
Gravity: 03
Report ID: 0257230
Contest Date:
Final Order:
Related Event Code (REC):
Emphasis:
| Type | Latest Event | Event Date | Penalty | Abatement Due Date | Citation Type | Failure to Abate Inspection |
|---|---|---|---|---|---|---|
| Penalty | I: Informal Settlement | 08/17/2010 | $455.00 | 07/27/2010 | Other | |
| Penalty | Z: Issued | 07/22/2010 | $650.00 | 07/27/2010 | Other |
Text For Citation: 02 Item/Group: 001 Hazard: FALLING
Section 6(a) of the Puerto Rico Occupational Safety and Health Act: The employer did not furnish employment and a place of employment which were free from recognized hazards that were causing or likely to cause death or physical harm to employees in that employees were exposed to: Tripping Hazard Reference: 10 OSH 1926.16(a) In no case shall the prime contractor be relived of overall responsibility for the compliance with the requirements of this part for all work to be performed under the contract. Seccion 6(a) de la Ley de Seguridad y Salud en el Trabajo de Puerto Rico: El patrono no proveyo empleo y un sitio de empleo libre de riesgos reconocidos que esten causando o que puedan causar muerte o dano fisico a los empleados, por cuanto empleados estaban expuestos a: Riesgo de Tropezones Referencia: 10 OSH 1926.16(a) En ningun caso se relevara al contratista general de la responsabilidad general de cumplir con los requisitos de esta parte para todos los trabajos que se realizaran bajo el contrato. LPC & D Inc. was the prime contractor and Bonn Construction Corp was subcontractor that had exposed employees to the hazards at the material wagon of the Jesus T. Pinero Remodelation Project, Canovanas PR. LPC & D Inc. as a general contractor failed to exercise his authority in order to enforce their safety and health program at the entire project. As a result of the lack of enforcement, it was observed that a subcontractor's (Bonn Construction Corp) employees accessed the wagon through a ramp made of plywood with crossed 2"x4" wood poles. The higher point of the ramp was 51 inches above the ground. The distance along the ramp between the foot and the top support was 64 inches and the width of the ramp was 52 inches. It was documented that the employees walked into the wagon to retrieve and store their tools and construction materials. Carrying these objects limited employees's visibility to the floor. The two by four (2"x4") wood poles that had a height of one and a half inches (1 1/2"), nailed to the ramp's surface represented a tripping hazard. Feasible abatement method to correct this hazard may include, but not are limited to: Construct a stairway with risers height and tread depth uniformly LPC & D Inc. era el contratista primario y Bonn Construction Corp era un subconstratista que tenia empleados expuestos a riesgos en el vagon de materiales del Proyecto de Remodelacion del Residencial Jesus T. Pinero, Canovanas PR. LPC & D Inc como Contratista General fallo en no ejercer su autoridad de forma que se asegurase el cumplimiento de su programa de seguridad y salud en el proyecto completo. Como resultado de la falta de su aplicacion, se observo que los empleados del subcontratista (Bonn Construction Corp.) accesaban al vagon atravez de una rampa hecha de paneles, cruzada por pedazos de 2"x4". El punto mas alto de rampa era de 51 pulgadas sobre el suelo. La distancia a lo largo de la rampa entre la base y la parte mas alta era 64 pulgadas y el ancho de la rampa era de 52 pulgadas. Se documento que los empleadoscaminaban hacia el vagon para recoger y almacenar sus herramientas y materiales de construccion. Los empleados cargando dichos objetos, limitaban su visibilidad al piso. Los palos de madera dos por cuatro (2"x4") que tenian una altura de una y media pulgada (1 1/2"), clavados a la superficie de la rampa representaban un riesgo de tropiezo. Metodo factible para corregir este peligro puede incluir, pero no se limita a lo siguiente: Construir una escalera donde el alto y la profundidad de la contrahuella sea uniforme.