Standard Cited: 19100119 D03 IB Process safety management of highly hazardous chemicals.
Inspection Nr: 311217426
Citation: 02001
Citation Type: Other
Abatement Status: I
Initial Penalty:
Current Penalty:
Issuance Date: 07/17/2009
Nr Instances: 4
Nr Exposed: 27
Abatement Date: 07/22/2009
Gravity: 01
Report ID: 0830100
Contest Date:
Final Order:
Related Event Code (REC):
Emphasis:
Text For Citation: 02 Item/Group: 001 Hazard: REFINERY
29 CFR 1910.119(d)(3)(i)(B) The employer did not compile process safety information which included accurate piping and instrument diagrams (P&IDs). a) No gauge as listed on P&ID 34A-004-D on the line from X-29 to the orifice chamber prior to X-353. The gauge (PG 120) had been removed and the 3/4" line had been capped. b) As listed on P&ID 34A-004-D at the bottom of the cone for X-353 the 3" y'ed stub line that should have been blind-flanged actually had a flange and reducer with a pipe extension and connector to a 3/4" open ended pipe. c) P&ID 34A-004-D: two 3/4" bypass level transmitter lines were not shown that were physically located on the south end of D-10. d) Valve 34-01 not shown as "LO" on P&ID 34A-005-D.
Translate