Violation Detail
Standard Cited: 19101001 J03 I Asbestos.
Inspection Nr: 1811631.015
Citation: 02001
Citation Type: Other
Abatement Status: Abatement Completed
Initial Penalty: $0.00
Current Penalty: $0.00
Issuance Date: 08/01/2025
Nr Instances: 1
Nr Exposed: 4
Abatement Date: 08/21/2025
Gravity:
Report ID: 0213600
Contest Date:
Final Order: 08/26/2025
Related Event Code (REC):
Emphasis:
Type | Latest Event | Event Date | Penalty | Abatement Due Date | Citation Type | Failure to Abate Inspection |
---|---|---|---|---|---|---|
Penalty | Z: Issued | 08/01/2025 | $0.00 | 08/21/2025 | Other |
Text For Citation: 02 Item/Group: 001 Hazard:
29 CFR 1910.1001(j)(3)(i):The building owner, facility owner, or employer did not determine the presence, location, and quantity of ACM or PACM at the worksite and did not exercise due diligence in complying with these requirements to inform employers and employees about the presence and location of asbestos-containing material (ACM) and presumed asbestos containing material (PACM): a) On or about 03/18/2025, in the Annealing Bay (BFS-Bar Finishing Storage East) Area; a large overhead pipe which runs the length of the Annealing Bay had damage to the insulation. Insulation was not tested to determine quantity of ACM (asbestos containing material), and or PACM (presumed asbestos containing material), including Thermal system insulation (TSI). ABATEMENT DOCUMENTATION REQUIRED.