Violation Detail
Standard Cited: 19100119 F01 I Process safety management of highly hazardous chemicals.
Inspection Nr: 1809314.015
Citation: 02001
Citation Type: Other
Abatement Status:
Initial Penalty: $0.00
Current Penalty: $0.00
Issuance Date: 08/18/2025
Nr Instances: 1
Nr Exposed: 180
Abatement Date: 10/03/2025
Gravity:
Report ID: 0316300
Contest Date: 09/10/2025
Final Order:
Related Event Code (REC):
Emphasis:
| Type | Latest Event | Event Date | Penalty | Abatement Due Date | Citation Type | Failure to Abate Inspection |
|---|---|---|---|---|---|---|
| Penalty | C: Contested | 09/10/2025 | $0.00 | 10/03/2025 | Other | |
| Penalty | Z: Issued | 08/18/2025 | $0.00 | 10/03/2025 | Other |
Text For Citation: 02 Item/Group: 001 Hazard:
29 CFR 1910.119(f)(1)(i):The employer did not develop and implement written operating procedures that provided clear instructions for safely conducting activities involved in each covered process consistent with the process safety information that addressed steps for each operating phase. a) Green Lines Multi Base Process, Remote Blocker Building: the employer failed to develop operating procedures that provided clear instructions that addressed steps for each operating phase for nonconforming material. The employer's document 4-07-757, Documentation of Nonconforming Material in the Green Lines Area, did not provide clear instructions that addressed steps for each operating phase of the multi based process, the document only included references to the single based process. Abatement certification required within 10 days after abatement date. The certification shall include a statement that abatement is complete, date and method of abatement, and states employees and their representatives were informed of this abatement.
Translate