Violation Detail
Standard Cited: 19100119 J04 IV Process safety management of highly hazardous chemicals.
Inspection Nr: 1744069.015
Citation: 02001
Citation Type: Other
Abatement Status:
Initial Penalty: $1,423.00
Current Penalty: $1,423.00
Issuance Date: 10/18/2024
Nr Instances: 1
Nr Exposed: 7
Abatement Date: 04/20/2026
Gravity:
Report ID: 0522500
Contest Date: 11/11/2024
Final Order: 10/20/2025
Related Event Code (REC):
Emphasis:
| Type | Latest Event | Event Date | Penalty | Abatement Due Date | Citation Type | Failure to Abate Inspection |
|---|---|---|---|---|---|---|
| Penalty | F: Formal Settlement | 10/20/2025 | $1,423.00 | 04/20/2026 | Other | |
| Penalty | C: Contested | 11/12/2024 | $1,423.00 | 11/07/2024 | Other | |
| Penalty | Z: Issued | 10/18/2024 | $1,423.00 | 11/07/2024 | Other |
Text For Citation: 02 Item/Group: 001 Hazard:
29 CFR 1910.119(j)(4)(iv): The employer shall document each inspection and test that has been performed on process equipment. The documentation shall identify the date of the inspection or test, the name of the person who performed the inspection or test, the serial number or other identifier of the equipment on which the inspection or test was performed, a description of the inspection or test performed, and the results of the inspection or test. a. On or about April 23, 2024, and at times prior, the employer did not document each inspection and test performed on process equipment associated with the CR1 covered process, including, but not limited to, the two-piece 1-inch compression fitting joint from the pipe assembly of the fluid feed piping into the CR1 reactor. As a result, employees working on and in the vicinity of the CR1 covered process were exposed to contact, explosion and fire hazards.