Standard Cited: 19100147 C05 II The control of hazardous energy (lockout/tagout).
Inspection Nr: 1738562.015
Citation: 02001
Citation Type: Other
Abatement Status: Abatement Completed
Initial Penalty: $1,423.00
Current Penalty: $500.00
Issuance Date: 09/30/2024
Nr Instances: 4
Nr Exposed: 9
Abatement Date: 03/28/2025
Gravity:
Report ID: 0134000
Contest Date: 10/21/2024
Final Order: 04/23/2025
Related Event Code (REC):
Emphasis:
Type | Latest Event | Event Date | Penalty | Abatement Due Date | Citation Type | Failure to Abate Inspection |
---|---|---|---|---|---|---|
Penalty | F: Formal Settlement | 04/23/2025 | $500.00 | 03/28/2025 | Other | |
Penalty | C: Contested | 10/22/2024 | $1,423.00 | 10/18/2024 | Other | |
Penalty | Z: Issued | 09/30/2024 | $1,423.00 | 10/18/2024 | Other |
Text For Citation: 02 Item/Group: 001 Hazard:
29 CFR 1910.147(c)(5)(ii):Lockout devices and tagout devices were not used for lockout and tagout purposes only: Location: MEPDC - SIPS a) On or about 8/22/24, a group lockout device was utilized in combination with non-Lockout/Tagout equipment for the purposes of removing overhead electrical equipment from service.