Violation Detail
Standard Cited: 19100029 B01 Fall protection systems and falling object protection-criteria and practices.
Inspection Nr: 1678763.015
Citation: 02001
Citation Type: Other
Abatement Status: Abatement Completed
Initial Penalty: $0.00
Current Penalty: $0.00
Issuance Date: 07/31/2023
Nr Instances: 1
Nr Exposed: 3
Abatement Date: 08/24/2023
Gravity:
Report ID: 0336000
Contest Date:
Final Order: 08/08/2023
Related Event Code (REC): C
Emphasis:
| Type | Latest Event | Event Date | Penalty | Abatement Due Date | Citation Type | Failure to Abate Inspection |
|---|---|---|---|---|---|---|
| Penalty | I: Informal Settlement | 08/08/2023 | $0.00 | 08/24/2023 | Other | |
| Penalty | Z: Issued | 07/31/2023 | $0.00 | 08/24/2023 | Other |
Text For Citation: 02 Item/Group: 001 Hazard:
29 CFR 1910.29(b)(1): The top edge height of top rails, or equivalent guardrail system members, were not 42 inches, plus or minus 3 inches, above the walking-working surface: a) Rdg Group, Inc.; Bfg Manufacturing Services, Inc.; Punxsutawney Finishing Works, Inc., Line 21 dryer area, on or about June 22nd, 2023 and times prior thereto: Employees were walking/working on the catwalk around the line 21 electroplating area. The catwalk was equipped with a guardrail system. The top rail height of the guardrail system was too low in that it was located approximately 36 inches from the deck of the catwalk. ABATEMENT CERTIFICATION REQUIRED: Abatement certification is required within 10 days after the abatement date noted on the citation (see below). This certification shall include a statement that abatement is complete, the date abatement was completed, method of abatement, and state that employees and their representatives were informed of this abatement.
Translate