Violation Detail
Standard Cited: 19260850 A Preparatory operations.
Inspection Nr: 1676614.015
Citation: 02001
Citation Type: Serious
Abatement Status: Not Completed - Worksite Changed
Initial Penalty: $156,259.00
Current Penalty: $16,131.00
Issuance Date: 12/13/2023
Nr Instances: 1
Nr Exposed: 11
Abatement Date: 10/25/2024
Gravity: 10
Report ID: 0626700
Contest Date: 01/09/2024
Final Order: 09/20/2024
Related Event Code (REC): A
Emphasis:
Type | Latest Event | Event Date | Penalty | Abatement Due Date | Citation Type | Failure to Abate Inspection |
---|---|---|---|---|---|---|
Penalty | F: Formal Settlement | 09/20/2024 | $16,131.00 | 10/25/2024 | Serious | |
Penalty | C: Contested | 01/10/2024 | $156,259.00 | 12/21/2023 | Willful | |
Penalty | Z: Issued | 12/13/2023 | $156,259.00 | 12/21/2023 | Willful |
Text For Citation: 02 Item/Group: 001 Hazard:
29 CFR 1926.850(a): An engineering survey was not performed by a competent person to determine the conditions of the framing, floors, and walls and the possibility of unplanned collapse of any portion of the structure prior to permitting employees to start demolition operations. a) On or about June 13, 2023, in Area P, where an engineering survey was not performed before engaging in demolishing activities, exposing employees to crush-by hazards.