Violation Detail
Standard Cited: 19100217 D09 I Mechanical power presses.
Inspection Nr: 1619056.015
Citation: 02001
Citation Type: Other
Abatement Status: Abatement Completed
Initial Penalty: $0.00
Current Penalty: $0.00
Issuance Date: 02/09/2023
Nr Instances: 1
Nr Exposed: 3
Abatement Date: 03/06/2023
Gravity:
Report ID: 0524500
Contest Date:
Final Order: 03/07/2023
Related Event Code (REC):
Emphasis:
Type | Latest Event | Event Date | Penalty | Abatement Due Date | Citation Type | Failure to Abate Inspection |
---|---|---|---|---|---|---|
Penalty | I: Informal Settlement | 03/07/2023 | $0.00 | 03/06/2023 | Other | |
Penalty | Z: Issued | 02/09/2023 | $0.00 | 03/06/2023 | Other |
Text For Citation: 02 Item/Group: 001 Hazard:
29 CFR 1910.217(d)(9)(i): The employer had not established a die setting procedure for mechanical power press(es) that would ensure compliance with 29 CFR 1910.217(c): On or about September 1, 2022, the employer had not established die setting procedures for the Fukui Presses.