Standard Cited: 19100253 E05 IV Oxygen-fuel gas welding and cutting.
Inspection Nr: 1608899.015
Citation: 02001
Citation Type: Other
Abatement Date: 11/15/2022 2
Initial Penalty: $0.00
Current Penalty: $0.00
Issuance Date: 10/19/2022
Nr Instances: 1
Nr Exposed: 14
Related Event Code (REC):
Gravity:
Report ID: 0316300
Contest Date:
Final Order: 11/15/2022
Emphasis:
Type | Latest Event | Event Date | Penalty | Abatement Due Date | Citation Type | Failure to Abate Inspection |
---|---|---|---|---|---|---|
Penalty | I: Informal Settlement | 11/15/2022 | $0.00 | 11/15/2022 | Other | |
Penalty | Z: Issued | 10/19/2022 | $0.00 | 11/15/2022 | Other |
Text For Citation: 02 Item/Group: 001 Hazard:
29 CFR 1910.253(e)(5)(iv): Hose connections were not clamped or otherwise securely fastened in a manner that would withstand, without leakage, twice the pressure to which they would normally be subjected in service, but in no case less than a pressure of 300 psi: a) Building #2 Tool Issue: On or about 07/21/2022, oxygen and propylene hoses were not pressure tested to at least 300psi, in that fittings were replaced and tested between 120 -200psi. Abatement certification required within 10 days after abatement date. The certification shall include a statement that abatement is complete, date and method of abatement, and states employees and their representatives were informed of this abatement.