Violation Detail
Standard Cited: 19100119 D03 I B Process safety management of highly hazardous chemicals.
This violation item has been deleted.
Inspection Nr: 1579863.015
Citation: 02001
Citation Type: Other
Abatement Status:
Initial Penalty: $1,163.00
Current Penalty: $0.00
Issuance Date: 07/21/2022
Nr Instances: 2
Nr Exposed: 10
Abatement Date: 08/25/2022
Gravity:
Report ID: 0625700
Contest Date:
Final Order: 08/29/2022
Related Event Code (REC):
Emphasis:
Type | Latest Event | Event Date | Penalty | Abatement Due Date | Citation Type | Failure to Abate Inspection |
---|---|---|---|---|---|---|
Penalty | I: Informal Settlement | 08/29/2022 | $0.00 | 08/25/2022 | Other | |
Penalty | Z: Issued | 07/21/2022 | $1,163.00 | 08/25/2022 | Other |
Text For Citation: 02 Item/Group: 001 Hazard:
29 CFR 1910.119(d)(3)(i)(B): Process Safety Information pertaining to the piping and instrumentation diagrams (P&ID) was not compiled, complete and accurate. a) This violation was most recently observed on or about February 21, 2022, when the employer did not ensure Process Safety Information (PSI) such as Piping and Instrumentation Diagram (P&ID) was complete and accurate including, but not limited to, the flange connections for the 6-inch check valve located on the inlet pipe of the ejector ##215-2801. b) This violation was most recently observed on or about March 29, 2022, when the employer did not ensure Process Safety Information (PSI) such as Piping and Instrumentation Diagram (P&ID) was complete and accurate including, but not limited to, the permanent pressure gauge on the 6-inch flare header pipe.