Violation Detail
Standard Cited: 19100147 C06 II The control of hazardous energy (lockout/tagout).
Inspection Nr: 1540180.015
Citation: 02001
Citation Type: Other
Abatement Status: Abatement Completed
Initial Penalty: $0.00
Current Penalty: $0.00
Issuance Date: 12/10/2021
Nr Instances: 1
Nr Exposed: 10
Abatement Date: 03/14/2022
Gravity:
Report ID: 0523900
Contest Date:
Final Order: 01/05/2022
Related Event Code (REC):
Emphasis:
Type | Latest Event | Event Date | Penalty | Abatement Due Date | Citation Type | Failure to Abate Inspection |
---|---|---|---|---|---|---|
Penalty | I: Informal Settlement | 01/05/2022 | $0.00 | 03/14/2022 | Other | |
Penalty | Z: Issued | 12/10/2021 | $0.00 | 01/04/2022 | Other |
Text For Citation: 02 Item/Group: 001 Hazard:
29 CFR 1910.147(c)(6)(ii):The employer did not certify that periodic inspections of the energy control procedures had been performed: (a) Throughout the big mill area; A record/certification of completion was not maintained to document that energy control (lockout/tagout) procedures were evaluated for equipment including, but not limited to: Banburys, mills, shear mixers, and conveyors.