Violation Detail
Standard Cited: 19260416 A01 General requirements.
Inspection Nr: 1517584.015
Citation: 02001
Citation Type: Willful
Abatement Status: Corrected During Inspection
Initial Penalty: $30,037.00
Current Penalty: $11,113.69
Issuance Date: 06/08/2021
Nr Instances: 1
Nr Exposed: 3
Abatement Date:
Gravity: 10
Report ID: 0214500
Contest Date: 09/15/2021
Final Order: 01/06/2022
Related Event Code (REC):
Emphasis:
Type | Latest Event | Event Date | Penalty | Abatement Due Date | Citation Type | Failure to Abate Inspection |
---|---|---|---|---|---|---|
Penalty | J: ALJ Decision | 01/06/2022 | $11,113.69 | Willful | ||
Penalty | C: Contested | 10/04/2021 | $30,037.00 | Willful | ||
Penalty | Z: Issued | 06/08/2021 | $30,037.00 | Willful |
Text For Citation: 02 Item/Group: 001 Hazard:
29 CFR 1926.416(a)(1): Employees were permitted to work in proximity to electric power circuits and were not protected against electric shock by de-energizing and grounding the circuits or effectively guarding the circuits by insulation or other means: a) Exterior - Park Ave. fa�ade: Employees were exposed to electric hazards while applying waterproof with rollers approximately 2 feet from a 4KV primary line, on or about 12/16/20 and thereafter.