Violation Detail
Standard Cited: 19260416 E01 General requirements.
Inspection Nr: 1479523.015
Citation: 02001
Citation Type: Other
Abatement Status: Corrected During Inspection
Initial Penalty: $276.00
Current Penalty: $165.60
Issuance Date: 07/13/2020
Nr Instances: 1
Nr Exposed: 2
Abatement Date:
Gravity:
Report ID: 0636900
Contest Date:
Final Order: 07/22/2020
Related Event Code (REC):
Emphasis:
| Type | Latest Event | Event Date | Penalty | Abatement Due Date | Citation Type | Failure to Abate Inspection |
|---|---|---|---|---|---|---|
| Penalty | I: Informal Settlement | 07/22/2020 | $165.60 | Other | ||
| Penalty | Z: Issued | 07/13/2020 | $276.00 | Other |
Text For Citation: 02 Item/Group: 001 Hazard:
29 CFR 1926.416(e)(1): Worn or frayed electric cords or cables were used. On the west side of the construction site, employees engage in masonry work utilized an extension cord with the outer sheathing split exposing internal wiring. The employees were exposed to electrical shock hazards.