Violation Detail
Standard Cited: 19100179 L03 I Overhead and gantry cranes.
Inspection Nr: 1461549.015
Citation: 02001
Citation Type: Serious
Abatement Status: Abatement Completed
Initial Penalty: $94,457.00
Current Penalty: $61,400.00
Issuance Date: 05/14/2020
Nr Instances: 8
Nr Exposed: 35
Abatement Date: 09/17/2021
Gravity: 10
Report ID: 0419700
Contest Date: 06/08/2020
Final Order: 10/04/2021
Related Event Code (REC): C
Emphasis:
Type | Latest Event | Event Date | Penalty | Abatement Due Date | Citation Type | Failure to Abate Inspection |
---|---|---|---|---|---|---|
Penalty | F: Formal Settlement | 10/04/2021 | $61,400.00 | 09/17/2021 | Serious | |
Penalty | C: Contested | 06/08/2020 | $94,457.00 | 06/03/2020 | Willful | |
Penalty | Z: Issued | 05/14/2020 | $94,457.00 | 06/03/2020 | Willful |
Text For Citation: 02 Item/Group: 001 Hazard:
29 CFR 1910.179(l)(3)(i): Unsafe conditions disclosed by the inspection requirements of paragraph (j) of this section were not corrected before operation of the crane was resumed: a. On or about February 7, 2020, in the receiving department, the employer continued to operate the Material Handling Systems (FLGL-001) 5-ton crane with deficiencies identified from the annual crane inspection. b. On or about February 7, 2020, in the fabrication shop, the employer continued to operate the Gorbel FLGL-002 crane with deficiencies identified from the annual crane inspection. c. On or about February 7, 2020, in the fabrication shop, the employer continued to operate the Gorbel FLGL-003 crane with deficiencies identified from the annual crane inspection. d. On or about February 7, 2020, in the fabrication shop, the employer continued to operate the Gorbel FLGL-004 crane with deficiencies identified from the annual crane inspection. e. On or about February 7, 2020, in the fabrication shop, the employer continued to operate the Harrington FLGL-005 crane with deficiencies identified from the annual crane inspection. f. On or about February 7, 2020, in the fabrication shop, the employer continued to operate the Gorbel FLGL-006 crane deficiencies identified from the annual crane inspection. g. On or about February 7, 2020, in the fabrication shop, the employer continued to operate the Gorbel FLGL- 007 crane with deficiencies identified from the annual crane inspection. h. On or about February 7, 2020, in the fabrication shop, the employer continued to operate the Gorbel FLGL- 008 crane with deficiencies identified from the annual crane inspection.