Violation Detail
Standard Cited: 19100119 D03 I B Process safety management of highly hazardous chemicals.
This violation item has been deleted.
Inspection Nr: 1372474.015
Citation: 02001
Citation Type: Other
Abatement Date: 08/15/2019
Initial Penalty: $0.00
Current Penalty: $0.00
Issuance Date: 06/28/2019
Nr Instances: 1
Nr Exposed: 3
Related Event Code (REC):
Gravity:
Report ID: 0625500
Contest Date: 07/23/2019
Final Order: 09/24/2019
Emphasis:
Type | Latest Event | Event Date | Penalty | Abatement Due Date | Citation Type | Failure to Abate Inspection |
---|---|---|---|---|---|---|
Penalty | F: Formal Settlement | 09/24/2019 | $0.00 | 08/15/2019 | Other | |
Penalty | C: Contested | 07/25/2019 | $0.00 | 08/15/2019 | Other | |
Penalty | Z: Issued | 06/28/2019 | $0.00 | 08/15/2019 | Other |
Text For Citation: 02 Item/Group: 001 Hazard:
29 CFR 1910.119(d)(3)(i)(B): The employer did not ensure the Process Safety Information (PSI) were complete and accurate including but not limited to the Piping and Instrument Diagrams (P&IDs). This violation was most recently observed on or about January 8, 2019, in the refrigeration engine room ER-2, when the employer failed to ensure the PSI were complete and accurate including but not limited to the P&ID drawing R3.3. Discrepancies were: a - Missing the pressure indicators on the pumps discharge lines from pressure vessels Low Temp Recirculator and High Temp Recirculator. b- Multiple valves were unidentified on the drawings.