Standard Cited: 19100147 C06 I The control of hazardous energy (lockout/tagout).
Inspection Nr: 1336524.015
Citation: 02001
Citation Type: Other
Abatement Date: 02/15/2019 2
Initial Penalty: $0.00
Current Penalty: $0.00
Issuance Date: 12/12/2018
Nr Instances: 1
Nr Exposed: 40
Related Event Code (REC):
Gravity:
Report ID: 0317900
Contest Date:
Final Order: 12/19/2018
Emphasis:
Type | Latest Event | Event Date | Penalty | Abatement Due Date | Citation Type | Failure to Abate Inspection |
---|---|---|---|---|---|---|
Penalty | I: Informal Settlement | 12/19/2018 | $0.00 | 02/15/2019 | Other | |
Penalty | Z: Issued | 12/12/2018 | $0.00 | 01/02/2019 | Other |
Text For Citation: 02 Item/Group: 001 Hazard:
29 CFR 1910.147(c)(6)(i): The employer did not conduct a periodic inspection of the energy control procedure at least annually to ensure that the procedure and the requirement of this standard were being followed: a) Production Work Area: On or about August 7, 2018, a periodic inspection of the energy control procedure was accomplished at least annually.