Violation Detail
Standard Cited: 19100212 A01 General requirements for all machines.
Inspection Nr: 1281084.015
Citation: 02001
Citation Type: Willful
Abatement Date: 06/12/2018 2
Initial Penalty: $44,342.00
Current Penalty: $21,000.00
Issuance Date: 05/31/2018
Nr Instances: 2
Nr Exposed: 4
Related Event Code (REC):
Gravity: 5
Report ID: 0523400
Contest Date:
Final Order: 06/26/2018
Emphasis:
Type | Latest Event | Event Date | Penalty | Abatement Due Date | Citation Type | Failure to Abate Inspection |
---|---|---|---|---|---|---|
Penalty | I: Informal Settlement | 06/26/2018 | $21,000.00 | 06/12/2018 | Willful | |
Penalty | Z: Issued | 05/31/2018 | $44,342.00 | 06/12/2018 | Willful |
Text For Citation: 02 Item/Group: 001 Hazard:
29 CFR 1910.212(a)(1): One or more methods of machine guarding was not provided to protect the operator and other employees in the machine area from hazards such as those created by point of operation, ingoing nip points, rotating parts, flying chips and sparks: (a) On or about December 5, 2017, the safety interlocks were bypassed on the Leadwell CNC machine (Model No. LTC-25AM and Serial No. L2TAB0605) which exposed employees to an entanglement hazard. (b) On or about December 5, 2017, the safety interlocks were bypassed on the Daewoo Puma CNC machine (Model No. 240MA and Serial No. P24M0065) which exposed employees to an entanglement hazard.