Violation Detail
Standard Cited: 19100305 G01 IV D Wiring methods, components, and equipment for general use.
Inspection Nr: 1265164.015
Citation: 02001
Citation Type: Other
Abatement Date: 3
Initial Penalty: $0.00
Current Penalty: $0.00
Issuance Date: 11/17/2017
Nr Instances: 1
Nr Exposed: 2
Related Event Code (REC):
Gravity:
Report ID: 0418600
Contest Date:
Final Order: 12/18/2017
Emphasis:
Type | Latest Event | Event Date | Penalty | Abatement Due Date | Citation Type | Failure to Abate Inspection |
---|---|---|---|---|---|---|
Penalty | I: Informal Settlement | 12/18/2017 | $0.00 | Other | ||
Penalty | Z: Issued | 11/17/2017 | $0.00 | Other |
Text For Citation: 02 Item/Group: 001 Hazard:
29 CFR 1910.305(g)(1)(iv)(D): Flexible cords and cables were attached to building surfaces: a) At 2307 US Hwy 31S, Bay Minette, AL: On or about September 19, 2017, the employer exposed employees to electrical shock hazards in that employees were allowed to walk and work around temporary flexible cord that was attached to the building in lieu of permanent fixed wiring.