Violation Detail
Standard Cited: 19260502 D06 I Fall protection systems criteria and practices.
Inspection Nr: 1264129.015
Citation: 02001
Citation Type: Other
Abatement Date: 03/20/2018 7
Initial Penalty: $0.00
Current Penalty: $0.00
Issuance Date: 03/08/2018
Nr Instances: 1
Nr Exposed: 1
Related Event Code (REC):
Gravity:
Report ID: 0524200
Contest Date:
Final Order: 04/04/2018
Emphasis:
Type | Latest Event | Event Date | Penalty | Abatement Due Date | Citation Type | Failure to Abate Inspection |
---|---|---|---|---|---|---|
Penalty | Z: Issued | 03/08/2018 | $0.00 | 03/20/2018 | Other |
Text For Citation: 02 Item/Group: 001 Hazard:
29 CFR 1926.502(d)(6)(i): Snap hooks were engaged directly to webbing, rope or wire rope when not designed for such connections: a) On or about September 14, 2017, an employee hoisting metal gutters onto the roof wrapped a vertical lifeline around a steel pipe on the roof and engaged the snap hook back onto the vertical lifeline.