Violation Detail
Standard Cited: 19100147 C04 I The control of hazardous energy (lockout/tagout).
Inspection Nr: 1224983.015
Citation: 02001
Citation Type: Other
Abatement Status: Abatement Completed
Initial Penalty: $0.00
Current Penalty: $0.00
Issuance Date: 06/23/2017
Nr Instances: 1
Nr Exposed: 1
Abatement Date: 07/13/2017
Gravity:
Report ID: 0418300
Contest Date:
Final Order: 07/13/2017
Related Event Code (REC):
Emphasis:
| Type | Latest Event | Event Date | Penalty | Abatement Due Date | Citation Type | Failure to Abate Inspection |
|---|---|---|---|---|---|---|
| Penalty | I: Informal Settlement | 07/13/2017 | $0.00 | 07/13/2017 | Other | |
| Penalty | Z: Issued | 06/23/2017 | $0.00 | 07/13/2017 | Other |
Text For Citation: 02 Item/Group: 001 Hazard:
29 CFR 1910.147(c)(4)(i): Procedures were not developed, documented and utilized for the control of potentially hazardous energy when employees were engaged in activities covered by this section: (a) On or about 04/12/2017 - Production Area, procedures were not developed and documented for employees performing servicing and maintenance on equipment such as, but not limited to, Seybold Cutter, Beck Rotary Cutter, Hickok Corner Cutter, and Screening machines, among others.